Genesis: rehearsal, launch sequence, and the first 90 days

Master Prompt 20 §4-5. Nothing here has been run for real. The real ceremony, the launch and every announcement each need an explicit “APPROVED: ”. The tool refuses a value-bearing chain id today anyway, because the shielded-pool circuit is unaudited (bins/genesis-ceremony).

Ceremony rehearsal (at least twice, on staging, with the real participants)

Section titled “Ceremony rehearsal (at least twice, on staging, with the real participants)”
  1. Freeze the inputs. A signed parameter file: chain id, timestamp, difficulty, allocations, treasury share, protocol-upgrade schedule (empty at launch), genesis validators with their signer public keys. Every participant signs the file’s BLAKE3 digest.
  2. Run genesis-ceremony with those inputs on an offline machine. It generates the root keys, funds the treasury and writes genesis.json and the commitment sheet.
  3. Independent reproduction. At least three participants recompute the genesis state root and block id from genesis.json on their own machines and compare with the commitment sheet. Any difference stops the ceremony.
  4. Validator readiness. Each genesis validator shows:
    • its remote signer running with slashing protection enabled from the first block (crates/signer, an empty history);
    • a pinned channel to its node;
    • maya2c-node --genesis genesis.json reporting the agreed genesis id.
  5. Record timings, every deviation, and the signatures. A rehearsal that deviated is repeated.
TStepRoleChannel
T−7 dParameter file frozen and signed; binaries tagged and reproducibly built on two machineslaunch director, release engineerprivate validator channel
T−2 dFinal rehearsal on stagingall genesis validatorsprivate channel + call
T−1 hValidators start nodes with the agreed genesis; signers onlinevalidatorscall
TGenesis timestamp passes; first blocks—status page
T+10 minCheck: finality reached, at least ⅔ of genesis stake participatinglaunch directorcall
T+1 hPublic announcement, only if every check passed and “APPROVED: announce” is givencommspublic

Abort criteria.

ConditionAction
Finality not reached within 10 minutescoordinated restart from genesis (docs/runbooks/coordinated-restart.md)
Genesis ids disagree between validatorsstop, recompute, no restart until resolved
Participation below ⅔ at T+30 minpause and call the missing validators; no public announcement
  • War room: 24/7 on-call for the first 2 weeks, a daily health report (SLOs, participation, incidents), and validator calls twice a week.
  • Conservative parameters: the fee market’s block target at its testing value (1 MiB), deferred modules off (ADR-016 activation heights u64::MAX), the validator cap of 100 (ADR-021). Governance raises limits only after a measured capacity review.
  • Hotfix process:
    1. a private patch to validators over the private channel;
    2. a coordinated upgrade at an activation height (a node without the patch halts cleanly: “upgrade required before height H”);
    3. public disclosure after the network is safe (SECURITY.md).
  • Reviews at days 7, 30 and 90, comparing each SLO and the economic model’s predictions (reports/18-economics.md) with what happened, and publishing the deviations.